On February 20, 2019, all the three Diesel Generators of the Iraq EPCC of Power Generation for Third River Water Intake Facilities Project successfully achieved normal power supply.

发电机组现场22(带水印).jpg



this EPCC Contract was awarded by Petronas on October 8, 2017 and came into effect on October 20, 2017. The total amount of the project is over 3 million USD. During project execution process, the excellent construction and management abilities demonstrated by POWER Project Team, as well as the outstanding results achieved, have been fully affirmed by the Owner. It is expected that the whole project will be finally delivered to Owner in March, 2019.